| Seeking to Realize Inherent Potential of Energy |
 |
|
 |
Procurement Activities |
 |
| Copyright(c) The Chugoku Electric Power Co.,Inc. |
|
 |
Standard Procurement Procedure
Chugoku Electric procures equipment and materials according to the following
Standard Procurement Procedure.
-
1. Prospective Supplier Selection
Prospective suppliers will generally be selected from Chugoku Electric’s
list of registered suppliers after the Group Management Div
receives a request for procurement from a section that needs equipment
or materials.
2. Bid Request
-
Chugoku Electric generally procures a product by means of competitive bidding,
whereby two or more potential suppliers are asked to offer proposals. Chugoku
Electric may request a proposal from a specific supplier, however, when
technical competence, patents, production capacity, equipment compatibility,
or other factor is of particular importance.
3. Bid Submission
-
Written proposals will be deemed valid only if they meet Chugoku Electric
deadlines, specifications, and conditions. Proposals based on specifications
different from those designated by Chugoku Electric will be considered,
however, if such alternative specifications satisfy Chugoku Electric functional
and performance requirements.
4. Supplier Selection and Price Negotiation
-
As a general rule, Chugoku Electric negotiates the final price of a contract
with the low bidder only. Unsuccessful bidders will be informed of the
results upon request.
5. Contract Conclusion
-
A contract should, in principle, be in compliance with the clauses prescribed
by Chugoku Electric when placing an order. When circumstances necessitate,
however, a contract may be drawn up in accordance with terms and conditions
agreed upon between Chugoku Electric and the supplier.
6. Delivery, Inspection, and Payment
-
Products will be inspected upon delivery by Chugoku Electric to confirm
conformance with contract stipulations. The supplier’s presence at such
inspection and/or assistance may be requested.
Payment is usually made in the month following acceptance. If warranted,
such as when long lead time is needed to manufacture a certain type of
product, Chugoku Electric will make scheduled disbursements or other special
payment arrangements.
7. Other
-
| (1) |
A party to the contract shall not divulge classified or otherwise sensitive
information in its possession without the express written consent of the
other party.
|
| (2) |
Chugoku Electric may also make formal claim for damages due to late delivery
of contracted goods.
|
| (3) |
Any questions or comments for Chugoku Electric at any stage of the procurement
procedure should be addressed to the Group Management Div. Chugoku Electric will respond to each party in good faith.
|
|
|