Construction and operation technology of photovoltaic power plant

  • We regard environmental efforts such as global warming as one of the important issues and implement initiatives aimed at realizing a low-carbon society.
  • As part of our efforts, we are promoting the introduction of renewable energy and building 2 solar power stations on the coast of the Seto Inland Sea and operating.

Fukuyama Photovoltaic Power Station

Location Fukuyama City, Hiroshima Prefecture
Output 3,000kW
Electric energy generated per year Approx. 3,680MWh
CO2 reduction amount Approx. 2,100 t-CO2 /year
Construction October 2010
Start of power operation December 2010
Solar cell area 4.5ha
Number of modules 16,544 sheets

Ube Photovoltaic Power Station

Location Ube City, Yamaguchi Prefecture
Output 3,000kW
Electric energy generated per year Approx. 3,520MWh
CO2 reduction amount Approx. 2,000 t-CO2 /year
Construction October 2013
Start of power operation December 2014
Solar cell area 4.0ha
Number of modules 12,690 sheets